Nscale loses Microsoft AI data center deal over UK power grid delays
Bitcoin mining offshoot Nscale saw Microsoft abandon a planned UK AI data center after the grid operator said sufficient power may not arrive until the 2030s.
Why it matters
The deal collapse highlights the severe power grid constraints slowing AI infrastructure deployment in the UK and demonstrates the execution risk for bitcoin miners pivoting to AI computing.
Key facts
Microsoft abandoned a planned AI data center project with Nscale in the UK
Reported by CoinDesk
The facility was to supply 50 megawatts to Azure by early 2027 using 23,040 Nvidia chips
50 megawattsReported by CoinDesk
UK Power Networks said sufficient power may not be available until the early-to-mid 2030s
Reported by CoinDesk
Nscale grew out of bitcoin mining firm Arkon Energy founded by Josh Payne
Reported by CoinDesk
UK data center grid-connection requests total about 73 gigawatts
73 gigawattsReported by CoinDesk
What happened
CoinDesk reports that Microsoft has abandoned a planned AI data center project with Nscale in Loughton, Essex. The facility was expected to deliver 50 megawatts of computing capacity to Microsoft's Azure cloud by early 2027 using 23,040 Nvidia chips. UK Power Networks, the local grid operator, informed Nscale that sufficient capacity may not be available until the early-to-mid 2030s. Nscale, which grew out of bitcoin mining firm Arkon Energy under founder Josh Payne, had announced the project alongside Microsoft and Nvidia last year. The setback illustrates the power and financing challenges bitcoin miners face when expanding into AI infrastructure, with UK data center grid-connection requests totaling approximately 73 gigawatts.
How the story developed
- First report
First report by CoinDesk
Bitcoin mining offshoot Nscale loses Microsoft AI deal as power delay stretches into 2030s
- Update
CoinDesk reports Microsoft abandons Nscale UK data center deal
Grid operator UK Power Networks indicated power may not be available until early-to-mid 2030s